St George’s University Hospital Trust

Project Title

Clients:       Hunters Architects
Project: Jenner Wing Level 1
Value: £2,500,000
Role: Cost Management Services
Principle: Mr Derek Bergin
Date: January 2016

 

Description:

 

To provide tender documentation, tender review and provide post contract cost management services for conversion of existing offices & labs to accommodate new administration & teaching facilities.

 

Key Achievements:

 

  • MPL’s Pre Tender Estimate identified shortfall with client’s budget (established by others). Accuracy of the PTE established to be within 10% of two lowest tenders.
  • Detailed Cost Plan enabled the client to establish objective value management identification.
  • Prompt tender evaluation & value engineering permitted the project to continue with minimal impact on project programme to meet start of academic year.

 

Project Particulars

Tags: Cost Management, Value Engineering